Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Exterior/Interior Clips/Sheathing/Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Not Ready | ||
| 02/27/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Canceled | ||
| 02/27/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Re-inspection required | Provide a untorn copy of approved plans, trimmers supporting headers have to be continuous without spacing, interior columns supporting GLB require post caps, install all hold downs per plan | |
| 03/01/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Partial Pass | Provide a untorn copy of approved plans, trimmers supporting headers have to be continuous without spacing, interior columns supporting GLB require post caps, install all hold downs per plan March 1st: interior columns require a post-cap, install all hold-downs |
|
| 03/06/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/16/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed |