Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - T22CM03546
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/21/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Little league field. ( A3,A4,A6,B3,B4,B5,B6) Soccer field. (S1,S2,S3,S4,S5,S6) Senior field. (A1,B1,C1,C2) LightStructureSystems. Okay for concrete placement. 2/21/2024 |
|
05/02/2024 | COT - HCBU - Excavation/Rebar/Zoning | Canceled | Canceled per contractor. 5/2/2024 | |
05/06/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 5/6/24: bathroom footings okay to place concrete | |
05/24/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Little league field. ( A3,A4,A6,B3,B4,B5,B6) Soccer field. (S1,S2,S3,S4,S5,S6) Senior field. (A1,B1,C1,C2) LightStructureSystems. Okay for concrete placement. 2/21/2024 5/6/24: bathroom footings okay to place concrete Canceled per contractor. 5/2/2024' 5/24/24: reinforcement per plan at 120' retaining wall south of ramp off of Silverbell rd., 76' reinforcement per plan at ramp footing off of silverbell rd. |
|
06/10/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Light pole bases total of two. One east of trash enclosure. Second at 60’ north east of trash enclosure. Rebar and depth per plan. Okay for concrete placement. 6/10/2024 |