Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - T22CM02468
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Engineering Final | Not Ready | ||
08/30/2023 | ENGR Engineering Final | Partial Pass | Roof drain splash pads and back ordered plants need to be completed prior to next inspection TC of O #1 | |
09/14/2023 | ENGR Engineering Final | Partial Pass | Level 4 TC of O partial pass Site Engineering Final needs to be called in when 100 % completed. | |
09/27/2023 | ENGR Engineering Final | Partial Pass | TC of O level 4 will recall inspection after all site items are completed and fencing is removed. | |
10/04/2023 | ENGR Engineering Final | Partial Pass | OK FOUR LEVEL FOUR 2-49 the entrance of the project need to be redone the handicap parking need to be redone the catch basin need to be look at by surveyors it looks like bust.the roof drain need to be lowered,the trash roll-off need to be removed. | |
11/27/2023 | ENGR Engineering Final | Passed |