Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|
| 09/27/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
TLUNDBERG |
Partial Approval |
Entered by NGARCIA3 - PA
Rooms 10 & 11, and corridor outside to the south exterior wall. Approved to pour. |
| 08/10/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - Partial Approval: theater #5. |
| 08/05/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - Partial Approval: Rooms 6, 7, and8. 1015. -Partial Approval: Elevator.
|
| 08/03/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - Partial Approval; Elevator pit and Room Nine. |
| 07/29/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
TLUNDBERG |
Partial Approval |
Entered by NGARCIA3 - PA. Unit 4 approved |
| 07/28/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Partial Approval |
Entered by RSALDAT1 - Partial Approval. Room Three. |
| 07/22/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Footings. Grid lines N.2-1.2, 2 and 2.8. Grid lines N-4.2, M-6.3, O-6.3, M-9, O-9, Q-2 and R.5-2 |
| 07/13/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, theater 1 ok for concrete placement. |
| 07/07/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Partial Approval |
Entered by NGARCIA3 - PA. Room two. |
| 07/06/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - PA. Room 10. |
| 07/05/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
RCHANDLER |
Cancelled |
Entered by VVERA1 - CA per text from Inspection Supervisor. |
| 12/07/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Footing for North stairs/ramp. |
| 12/12/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
|
| 12/21/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
|