Inspection Status: Not Ready
Inspection History: COT - LCBU - Roof Nailing
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Roof Nailing |
|
Not Ready |
|
| 07/14/2022 |
COT - LCBU - Roof Nailing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Inspection performed 13 July. |
| 07/13/2022 |
COT - LCBU - Roof Nailing |
JBURGE |
Approved |
Entered by VVERA1 - Approved. Ok to finish placing shingles on roof surface.