Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Masonry Pregrout
Permit Number - T22CM01443
Inspection Description - COT - RSBU - Masonry Pregrout
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - RSBU - Masonry Pregrout | Not Ready | ||
01/03/2024 | COT - RSBU - Masonry Pregrout | Not Ready | 11/27/23: okay to proceed to second lift 1/3/23: not ready |
|
01/05/2024 | COT - RSBU - Masonry Pregrout | Partial Pass | East portion of house is topped-out at 18’ 8”. Ok to grout progress areas. CMU walls to be masonry capped. | |
01/11/2024 | COT - RSBU - Masonry Pregrout | Partial Pass | West portion of house; CMU walls at 14’6” - 18’6”. Ok to grout progress areas. | |
01/17/2024 | COT - RSBU - Masonry Pregrout | Partial Pass | Exterior CMU walls are topped out. OK to grout progress areas. | |
04/12/2024 | COT - RSBU - Masonry Pregrout | Passed | ||
11/27/2023 | COT - RSBU - Masonry Pregrout | Partial Pass | 11/27/23: okay to proceed to second lift | |
12/08/2023 | COT - RSBU - Masonry Pregrout | Partial Pass | CMU walls at 4’ - 8’. Ok to grout progress areas. | |
12/19/2023 | COT - RSBU - Masonry Pregrout | Partial Pass | West portion of building at 8’ - 12’; East portion of building at 4’ - 8’. Ok to grout progress areas. |