Inspection Status: Not Ready
Inspection History: COT - LCME - Mechanical Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCME - Mechanical Final |
|
Not Ready |
|
| 10/17/2022 |
COT - LCME - Mechanical Final |
RSHERRY |
Partial Approval |
Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED |
| 03/21/2022 |
COT - LCME - Mechanical Final |
RSHERRY |
Prior to Final Inspectn |
Entered by RSHERRY1 - AIR BALANMCE REPORT REQUIRED |
| 11/03/2022 |
COT - LCME - Mechanical Final |
|
Partial Pass |
All units on this permit need line sets secured, 15 amp max breakers on condensing units, toilets and sinks caulked in, blanks in any open spaces in sub panels, unit 2 has 3 outlets not working, m/c cable secured with strain relief and routed properly, and suggest a shelf be put over water heater. |
| 11/23/2022 |
COT - LCME - Mechanical Final |
|
Passed |
|