Inspection Status: Not Ready
Inspection History: Pool/Spa - Pre-Gunite
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
Pool/Spa - Pre-Gunite |
|
Not Ready |
|
| 02/02/2023 |
Pool/Spa - Pre-Gunite |
|
Not Ready |
rebar needs minimum 3” of clearance from ground and edges of earth. loose rebar in bench area. |
| 02/08/2023 |
Pool/Spa - Pre-Gunite |
|
Passed |
rebar is properly tied and supported by dobes to maintain clearance from earth. Recommend contractor trim tree roots flush with soil prior to gunite application. |