Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Recurring
| Date |
Description |
Inspector |
Results |
Comments |
| 09/22/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Underground gas work has been completed. Area has been saw cut for removals. Asphalt limits were set by myself and agreed-upon for moratorium pave |
| 08/19/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Underground gas work has been completed. Asphalt moratorium pave still needed |
| 03/16/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in place. Roadway will require a moratorium repair |
| 03/01/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Underground gas work has been completed. Asphalt repair still needed. Moratorium repairs will be required |
| 02/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Underground gas work has been completed. Asphalt has been saw cut. Moratorium repairs will be needed |
| 01/24/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in place. Moratorium patch standards will be held |
| 12/23/2021 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Underground gas work has been completed. Temporary asphalt patch still in place. Moratorium patch is required on Herbert. |
| 12/02/2021 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - NPL on site today. No pre-con was held and moratorium was overlooked. Contractor will need to pave to moratorium standards |
| 10/06/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Asphalt repairs still needed. Work was completed in new asphalt. Paving moratorium exists |
| 11/29/2021 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Underground gas work has been completed. Sidewalk repairs still necessary |
| 12/08/2022 |
TRSP - ROW - Recurring |
|
Complete (Recurring) |
|