Permit: T21RW04859

Parcel: 11705069D


Addresses:

340 N 6TH AV

Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Date Description Inspector Results Comments
10/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Electrical conduit has been installed. Roadway repairs still necessary
09/13/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All underground work has been completed. Sundt construction took over project, and understands they will need to repair Roadway.
08/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Underground electrical work has been completed. Asphalt repair still needed
05/26/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All underground electric work completed. Roadway repairs still needed
02/04/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All electric underground completed. Temporary asphalt patch still in roadway
12/07/2022 TRSP - ROW - Recurring Complete (Recurring)
12/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All electric work contained inside of PIA property boundaries