Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Recurring
Permit Number - T21RW01453
Inspection Description - TRSP - ROW - Recurring
Inspection Status - Re-inspection required
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/13/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Pole placed and color matched according to plans. Landscaping has been restored. Site passes ROW inspection. | |
08/13/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.southwest scheduled for barricade PU | |
08/06/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Vertical one placed pole and are placing light a d arm for light. | |
08/06/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
06/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Pole ha yet to be placed. | |
06/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Chain link set around site barricades pulled from roadway | |
06/11/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Verticle one installed hand boxes and rebar caisson for pole placement. Set to pour concrete and slurry at 1330. | |
06/11/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
05/28/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Meeting took place on 2616 N 15th Av. People attending meeting were Alex and James from DEIH, Nick Dominguez and Nancy Carrillo from Vertical one, Larry Castro from VZN and Caitlin from Southwest barricades. Electric pole will be installed where existing pole is, also will have same elevation. Vertical one will save mast arm for new pole to install light. No meter box for this sight, power will come from jbox. Vertical one was notified that native pants and trees were not to be removed. Spoke to Nancy Carrillo from Vertical one and stated would send the ROW Precon meeting sheets filled out and pics of notification of work to neighbors via email to Dan Robertson, Travis Horness and myself. |
|
05/28/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control will be set as planed also notified Vertical one that if the road doesnt have 20’ft of clearance they would need flagmen for this sight. |