Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T21RW01336

Parcel: Unknown


Addresses:

3347 N 1ST AV


Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T21RW01336

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
06/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Vertical one finished pole inspections and antenna inspection. Site cleaned and swept up. Southwest barricades removed barricades from roadway and staged for set up tomorrow evening at 2000 for concrete work. ROW clean and clear of debris sidewalk closed signs and Ada wall have been removed from site.
06/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Vertical one cleaning new concrete pour and testing antennas. Tomorrow 6-15 concrete joint will be saw cut and power washed vacuumed and barricades will be removed from site and ready for final ROW inspection
06/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Vertical one connecting light and fiber. Placed cover over pole base. Cleaned and removed forms from concrete pour. Ada wall set to pick up tomorrow day.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Vertical one installing pole connecting light and running lines. Traffic control appears to be in accordance with plans. Pole set up and vertical one running all electrical and placing light.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Concrete set up too quickly. Removed 2.5 yards that couldn’t be finished. Cleaned road way and driveway for businesses. Pouring tomorrow with approval from Daniel Robertson
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pouring 20’x12’ concrete slab where existing concrete was removed. Expansion joints placed around all sides. Slope is at 2.7% which matches existing concrete from driveway to curb. Joints and n driveway east and west will follow through to new concrete and one fire joint will be placed center of concrete north to south per Dan Robertson. Calportland 2500 psi concrete temperature was at 81°f upon beginning of pour at 1210.
06/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pour concrete and slurry for pole and hand boxes concrete temp 79°f slump 3.0” strength cylinders made by WTI. Late pick up on traffic control take down began at 1545.
06/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Vacuum trenching for pole caisson and hand boxes.
06/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pole placed. Sidewalk has been restored. ROW passes inspection.
05/27/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pre con meeting. Remove old pole and place new Verizon’s antenna. Concrete must be replaced joint to joint unless approved otherwise.
06/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.