Inspection History Details
Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Recurring
Permit Number - T21RW01320
Inspection Description - TRSP - ROW - Recurring
Inspection Status - Re-inspection required
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/07/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - ROW appears to be in accordance with plans. ROW passes inspection. Sidewalk and landscaping restored. | |
06/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Pole is placed. Sidewalk is replaced and restored. Landscaping restoration needs to be completed. Backfill east of face of pole to sidewalk level and add decorative rock to sidewalk matching for at and t store. | |
07/07/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. | |
06/03/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - New concrete truck came temp was 84°. Poured pole caisson. Truck driver cleaned out over sidewalk. Asked him to clean out on tarp told me to provide clean out or he will clean out wherever he wants. Notified verticle one of the issue. Storm drains properly covered for pour. | |
06/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup. | |
06/03/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Concrete to be poured for pole. Concrete temp was 96°f according WTI. Truck rejected. Verticle one did not order concrete with ice or chilled water. New truck being dispatched with ice and chilled water. | |
06/03/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
06/02/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Vacuum trenched and removed caisson. Ontonie to vacuum trench and put in hand boxes and rebar. | |
06/03/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
05/27/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Precon meeting. Remove old pole and replace with antenna pole for Verizon. Storm drain in roadway will need to Be covered and watched while Working. Landscaping must be restored. Bricks around electric handbox to be leveled and fixed. |
|
06/02/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. |