Permit: T21RW01047

Parcel: Unknown


Addresses:

1097 E WAVERLY ST


Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T21RW01047

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
07/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pole placed and matches color. Landscaping and asphalt restored. Row appears to be according to the plans and passes final inspection.
06/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Concrete poured for pole foundation. Awaiting pole removal and over head. Pole not placed. Bore completed for electrical pedestal.
07/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
06/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Vertical one preparing for concrete pour and slurry. B line drilling is boring electrical. James from DEIH notified them of using the wrong color sleeve (orange) and must place red or grey for electrical. Rey Silva called Brian Ripley with truenet to get the proper material onsite.
06/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Verticle one placed fence with tarp to prevent tree from getting debris. Placing hand boxes and rebar caisson for pole.
06/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Verticle one to begin vacuum trench. Notified them to please set up tarp or fencing to prevent tree with remembrance shrine from
Getting mud and debris thrown on tree.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pre construction meeting mesquite tree near pole is a shrine for the death of a person. Tree must be properly protected from work. Replace old pole with new pole and light. All boring must be done in street. Pedistole to be placed near alley entrance by pole. Alley closed signs must be added to traffic control. Verticle one will notify fire department of street closure and waste management for alley closure to have alley available for trash pickup.
06/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.