Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Recurring
Permit Number - T21RW00303
Inspection Description - TRSP - ROW - Recurring
Inspection Status - Re-inspection required
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/17/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Underground water installation has been completed. Temporary asphalt patch still in roadway | |
| 03/29/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Underground waterworks have been installed. Moratorium repairs still needed. Contractor will repave Silverbell when neighborhood is paved | |
| 03/15/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - All water crossings have been installed for new neighborhood. Moratorium pave still needed.Contractor will repave SilverBell when entrance to neighborhood has been paved | |
| 02/17/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Water crossings have been installed for new subdivision. Moratorium repair still needed. Moratorium repair will not be completed until after new entrance to subdivision has been installed | |
| 07/21/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Underground water has been installed. Temporary asphalt patch across roadway. I talked with Lorenzo from Dirtworks who stated they will do the moratorium pave when the new subdivision gets paved. I informed Lorenzo that will be a while and to maintain the permit. | |
| 03/09/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - What a work in progress. No issues with barricades set up. Flagman in use. Pipe installation going slow. | |
| 03/04/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Correction Required - Call-out for failing plates in roadway. Dirtworks and Trafficade arrived to divert traffic around Hazard. Will backfill and re-plate 3/4. | |
| 02/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued - Project on hold. Encountered concrete encased Fiber Optic line. Need redesign approved by Tucson Water. Dirtworks to place bump signs at plated excavation. | |
| 01/05/2023 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 02/02/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued - Meeting to discuss water crossings on Silverbell. Road under pavement moratorium. Plates to be milled in. Flagger setup with speed reduction. Preconstruction checklist sent to Tyler at Dirt Works. Waiting on conformation from Archeologist Jodie Brown before proceeding. | |
| 02/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. | |
| 04/17/2024 | TRSP - ROW - Recurring | Re-inspection required |