Inspection Status: Passed
Inspection History: FCON – OH Piping & Hydro
| Date |
Description |
Inspector |
Results |
Comments |
| 11/23/2021 |
FCON – OH Piping & Hydro |
wmotto1 |
Approved |
Entered by WMOTTO1 - 1. The overhead 200lb test approved via face time. Need to verify placement at final. This is for the 2nd floor.
2 inch drain test 65-65-65
water flow set alarm off in 45 seconds |
| 11/03/2021 |
FCON – OH Piping & Hydro |
wmotto |
Partial Approval |
Entered by WMOTTO1 - 200 pound test first floor approved. Ok to cover pipe on the first floor |