Permit: T21FC00104


Addresses:

3550 E CORONA RD


Inspection Status: Approved

Inspection History: FIRE SPKLR - UG, PIPING, HYDRO

Permit Number - T21FC00104

Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO

Inspection Status - Approved

Date Description Inspector Results Comments
07/13/2021 FIRE SPKLR - UG, PIPING, HYDRO Approved Hydro test completed on 12" supply line.
200 psi
06/22/2021 FIRE SPKLR - UG, PIPING, HYDRO Cancelled
06/16/2021 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 7th inspection - visual inspection of the 12" supply pipe from the valve in the parking lot to the pump room.
Ok to backfull pipe.

*Note-Hydro test @ 200psi still needed.
05/25/2021 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 6th inspection - All the 10" line around the building has benn hydro tested. This supplies the hydrants as well as the 4 interior risers.
The 12" supply line to the pump still needs to be installed and then tested.

All lines still need to be flushed.
05/12/2021 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 5th inspection
Tie in on SW corner of building and 50' run on west side of building
OK to backfill
04/23/2021 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Observed fire line on south side of building approx. 300'.
Observed 50' on west side of buildind.
Pressure test will take place after line is buried
They have had 4 inspections.
03/16/2021 FIRE SPKLR - UG, PIPING, HYDRO Not ready for Inspection 1ST inspection. UG not under pressure