Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T21CM09776

Parcel: 140260390

Inspection Status: Not Ready

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - T21CM09776

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning  Not Ready
02/06/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 24 each F-1 column footings at GL: B - C/2 - 14. OK to place concrete in progress areas.
02/11/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
02/13/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
02/14/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15,
02/19/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
02/27/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.
03/04/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 3-4-25, reinforcement per plans on Building 1 for continuous footers east side. Okay to pour
03/18/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 3-18-25, reinforcement for footing on Building 2's east side and south end up to grid 10.5 verified per plans-okay to pour progress areas.
03/20/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 3-20-25, reinforcement (footing) on Building 2- East side grid lines 1-7 West side 2-8 per plans. Okay to pour.
04/03/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 4-3-25, reinforcement per approved plans for pads#1,2, 56-72 -okay to pour 1 concrete.
05/07/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 5-7-25, reinforcement on ramps #4-9 & 13-18 verified per plans. Okay to pour concrete.
05/15/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 5-15-25, reinforcement on panels 28-49 & panel 57 verified per plans. Okay to pour concrete.
Note: have all imbeds complete at time of inspection or only schedule when ready.
06/05/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 6-5-25: reinforcement for closure pour back at north & midway point along east side of Building 1 verified per plans. Okay for concrete pour at progress areas.
06/11/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 6-11-25: reinforcement for closure pour back along east side of Building 1 verified per plans. Reinforcement on Building 1 dock leveler pit's 1, 2, 4-9 also verified per plans and all are okay to pour concrete.
06/13/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 6-13-25: reinforcement on 7 dock ramp footers for Building 2 verified per plans. Okay to concrete at progress areas. Note: trash enclosures must be scheduled under development plan permit.
06/17/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.
3-4-25, reinforcement per plans on Building 1 for continuous footers east side. Okay to pour
3-18-25, reinforcement for footing on Building 2's east side and south end up to grid 10.5 verified per plans-okay to pour progress areas.

3-20-25, reinforcement (footing) on Building 2- East side grid lines 1-7 West side 2-8 per plans. Okay to pour.

4-3-25, reinforcement per approved plans for pads#1,2, 56-72 -okay to pour concrete.
5-7-25, reinforcement on ramps #4-9 & 13-18 verified per plans. Okay to pour concrete.
5-15-25, reinforcement on panels 28-49 & panel 57 verified per plans. Okay to pour concrete.
Note: have all imbeds complete at time of inspection or only schedule when ready.

6-5-25: reinforcement for closure pour back at north & midway point along east side of Building 1 verified per plans. Okay for concrete pour at progress areas.
6-11-25: reinforcement for closure pour back along east side of Building 1 verified per plans. Reinforcement on Building 1 dock leveler pit's 1, 2, 4-9 also verified per plans and all are okay to pour concrete.
6-13-25: reinforcement on 7 dock ramp footers for Building 2 verified per plans. Okay to concrete at progress areas. Note: trash enclosures must be scheduled under development plan permit
6/17/25:Rebar for closure strip building 1. GL A/1-9
06/20/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.
3-4-25, reinforcement per plans on Building 1 for continuous footers east side. Okay to pour
3-18-25, reinforcement for footing on Building 2's east side and south end up to grid 10.5 verified per plans-okay to pour progress areas.

3-20-25, reinforcement (footing) on Building 2- East side grid lines 1-7 West side 2-8 per plans. Okay to pour.

4-3-25, reinforcement per approved plans for pads#1,2, 56-72 -okay to pour concrete.
5-7-25, reinforcement on ramps #4-9 & 13-18 verified per plans. Okay to pour concrete.
5-15-25, reinforcement on panels 28-49 & panel 57 verified per plans. Okay to pour concrete.
Note: have all imbeds complete at time of inspection or only schedule when ready.

6-5-25: reinforcement for closure pour back at north & midway point along east side of Building 1 verified per plans. Okay for concrete pour at progress areas.
6-11-25: reinforcement for closure pour back along east side of Building 1 verified per plans. Reinforcement on Building 1 dock leveler pit's 1, 2, 4-9 also verified per plans and all are okay to pour concrete.
6-13-25: reinforcement on 7 dock ramp footers for Building 2 verified per plans. Okay to concrete at progress areas. Note: trash enclosures must be scheduled under development plan permit
6/17/25:Rebar for closure strip building 1. GL A/1-9
6/20/25: rebar for closure strip building 1 GL A9-15.
07/01/2025 COT - LCBU - Excavation/Rebar/Zoning  Not Ready 7/1/2025 not ready.
07/02/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.
3-4-25, reinforcement per plans on Building 1 for continuous footers east side. Okay to pour
3-18-25, reinforcement for footing on Building 2's east side and south end up to grid 10.5 verified per plans-okay to pour progress areas.

3-20-25, reinforcement (footing) on Building 2- East side grid lines 1-7 West side 2-8 per plans. Okay to pour.

4-3-25, reinforcement per approved plans for pads#1,2, 56-72 -okay to pour concrete.
5-7-25, reinforcement on ramps #4-9 & 13-18 verified per plans. Okay to pour concrete.
5-15-25, reinforcement on panels 28-49 & panel 57 verified per plans. Okay to pour concrete.
Note: have all imbeds complete at time of inspection or only schedule when ready.

6-5-25: reinforcement for closure pour back at north & midway point along east side of Building 1 verified per plans. Okay for concrete pour at progress areas.
6-11-25: reinforcement for closure pour back along east side of Building 1 verified per plans. Reinforcement on Building 1 dock leveler pit's 1, 2, 4-9 also verified per plans and all are okay to pour concrete.
6-13-25: reinforcement on 7 dock ramp footers for Building 2 verified per plans. Okay to concrete at progress areas. Note: trash enclosures must be scheduled under development plan permit
6/17/25:Rebar for closure strip building 1. GL A/1-9
6/20/25: rebar for closure strip building 1 GL A9-15.

7/1/2025 not ready.
7/2/2025: entry corner column reinforced per plan at building one south east and north east corners.
11/10/2025 COT - LCBU - Excavation/Rebar/Zoning  Passed 11-10-25: approved.