Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCEL - Electrical Progress |
|
Not Ready |
|
| 10/27/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
10-27-25: electrical for SES,Transformers and fire pump verified per plans. Verified labeling on panels & water bonding. Secondary feeders will be pulled sometime next week and contractor will schedule an electrical clearance. |
| 11/05/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
11-5-25: feeders torqued to specs. Okay to energize SES-Socket 1. |
| 11/10/2025 |
COT - LCEL - Electrical Progress |
|
Passed |
11-10-25: approved. |