Permit: T21CM09775

Parcel: 140260390

Inspection Status: Not Ready

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - T21CM09775

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning  Not Ready
02/13/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/13/25: footing 3 at GL B-C/6 reinforced per plan ok to proceed.
02/27/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/13/25: footing 3 at GL B-C/6 reinforced per plan ok to proceed.
2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.
03/06/2025 COT - LCBU - Excavation/Rebar/Zoning  Re-inspection required 3-6-25, #5 rebar missing at columns-grid line A-D/5-10. Reinspection required.
Note: please schedule all future inspections on Building 1 under Building 1
03/11/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/13/25: footing 3 at GL B-C/6 reinforced per plan ok to proceed.
2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.

3-6-25, #5 rebar missing at columns-grid line A-D/5-10. Reinspection required.
Note: please schedule all future inspections on Building 1 under Building 1
3/11/25: reinforcement per plans at slab on grade at GL A-D/5-10 building
03/24/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/13/25: footing 3 at GL B-C/6 reinforced per plan ok to proceed.
2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.

3-6-25, #5 rebar missing at columns-grid line A-D/5-10. Reinspection required.
Note: please schedule all future inspections on Building 1 under Building 1
3/11/25: reinforcement per plans at slab on grade at GL A-D/5-10 building 1
3/24/25: reinforcement per plans at slab on grade at building 1 for final pour .
04/09/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/13/25: footing 3 at GL B-C/6 reinforced per plan ok to proceed.
2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.

3-6-25, #5 rebar missing at columns-grid line A-D/5-10. Reinspection required.
Note: please schedule all future inspections on Building 1 under Building 1
3/11/25: reinforcement per plans at slab on grade at GL A-D/5-10 building 1
3/24/25: reinforcement per plans at slab on grade at building 1 for final pour .
4/9/25: reinforcement per plans at tilt up panels (3-17,19,73,2) ok to proceed with pour 2.
04/11/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2/13/25: footing 3 at GL B-C/6 reinforced per plan ok to proceed.
2/11/25: 16 spread footers reinforced per plan. Ok to proceed
2/13/25: Footing 3 per plan at GL B-C/6 ok to proceed with concrete placement.
2/14/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-15, A.5-D/15.
2/19/25: Building 1 continuous footer (F5) reinforcement per plan from GL D/9-1, C-D/1.
2/27/25: reinforcement per plan at continuous footers on GL A-D/1 and D/1-3.

3-6-25, #5 rebar missing at columns-grid line A-D/5-10. Reinspection required.
Note: please schedule all future inspections on Building 1 under Building 1
3/11/25: reinforcement per plans at slab on grade at GL A-D/5-10 building 1
3/24/25: reinforcement per plans at slab on grade at building 1 for final pour .
4/9/25: reinforcement per plans at tilt up panels (3-17,19,73,2) ok to proceed with pour 2.
4/11/25: reinforcement per plan at tilt up panels for pour 3. Ok to proceed.
04/16/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 4-16-25, reinforcement for panels 55-40 on Building 1 verified per approved plans. Okay to pour concrete.
05/01/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 5-1-25, reinforcement on Building 1 ramp wall footing located on the south west side verified per plans. Okay to pour concrete.
05/21/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 5-21-25: reinforcement for panels 1-10 & 50-56 verified per plans on Building 2. Okay to pour concrete.
07/01/2025 COT - LCBU - Excavation/Rebar/Zoning  Not Ready 7/1/2025 not ready.
07/07/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 7-7-25: reinforcement for 2 columns located on Building 2 along the northwest & southwest corners verified per plans. Okay to pour
07/10/2025 COT - LCBU - Excavation/Rebar/Zoning  Canceled 7-10-25: canceled by contractor.
07/14/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 7-14-25: reinforcement for Building 2 Slab on grade rebar closure strip along the eastside verified per plans. Okay to pour back.
07/16/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 7-16-25: reinforcement on Building 2's west side closure strip at midpoint together with the reinforcement at the shear wall verified per plans. Okay for pour back.
07/17/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 7-17-25: reinforcement on Building 2 south side & east section of the closure strip verified per plans. Okay for pour back.
11/06/2025 COT - LCBU - Excavation/Rebar/Zoning  Passed 11-6-25: approved.