Date Description Inspector Results Comments
10/27/2022 COT - LCBU - Framing Not Ready
07/29/2025 COT - LCBU - Framing Partial Pass 7-29-25: metal framing inspection for Building 1 electrical & fire pump room verified per plans. Okay to continue with construction at progress areas.
08/22/2025 COT - LCBU - Framing Partial Pass 8-22-25: partial pass on Building 2's drywall inspection for electrical/fire pump room. Northside of exterior metal framing around entry is missing a couple of sections of drywall. Okay to tape & texture progress areas.
08/27/2025 COT - LCBU - Framing Partial Pass 8-27-25: Building 1 drywall nailing inspection for room east of a FACP located on southwestern area of site. Okay to tape & texture west and north walls.
09/26/2025 COT - LCBU - Framing Canceled 9-26-25: canceled by contractor.
10/07/2025 COT - LCBU - Framing Re-inspection required Final screw inspection.
11/06/2025 COT - LCBU - Framing Passed 11-6-25: framing approved.