Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCEL - Electrical Progress |
|
Not Ready |
|
| 04/07/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Information only; will reschedule for 8 April 2025 for pre-con meeting |
| 08/07/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
BLDG 2 in wall electrical at riser room and electrical room. Approved. Okay to proceed progress areas. 8/7/2025 |
| 08/21/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
8-21-25: Building 2-verified all can lights at soffit areas. Secure mc cable off grid and schedule inspection prior to installation of drywall. |
| 10/27/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
10-27-25: electrical for SES & Transformers verified per plans. Verified labeling on panels & water bonding. Secondary feeders will be pulled sometime next week and contractor will schedule an electrical clearance. |
| 11/05/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
11-5-25: feeders torqued to specs-okay to energize SES- Socket 1. |
| 11/18/2025 |
COT - LCEL - Electrical Progress |
|
Passed |
11-18-25: approved. |