Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Building Progress |
|
Not Ready |
|
| 06/16/2022 |
COT - LCBU - Building Progress |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Attic level; new 2" x 10" beams installed at 24" on center by clips and bolts; per plans. Roof level: crickets and scuppers installed as per plans. Ok to dry in roof system. |
| 05/13/2022 |
COT - LCBU - Building Progress |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - -PA. To be Inspected J1 J3 2nd floor tension ties blocking and strapping . |
| 05/13/2022 |
COT - LCBU - Building Progress |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - PA. Level two floor joist NW room. |
| 05/03/2022 |
COT - LCBU - Building Progress |
RCHANDLER |
Partial Approval |
Entered by NGARCIA3 - PA. Tension ties North half of Building. |
| 04/26/2022 |
COT - LCBU - Building Progress |
WGALLAGHER |
Partial Approval |
Entered by NGARCIA3 - Partial approval for F1 footing for center load bearing wall ok to place concrete |
| 04/20/2022 |
COT - LCBU - Building Progress |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - -PA. Looked at footings under floor as marked on plans. Provide stamped detail for RFI on other footings. Also floor jousting as marked on plans. |
| 02/23/2023 |
COT - LCBU - Building Progress |
|
Passed |
|