Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Progress
Permit Number - T21CM09221
Inspection Description - COT - LCBU - Building Progress
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Building Progress | Not Ready | ||
08/10/2022 | COT - LCBU - Building Progress | SCARRAZCO | Not ready for Inspection | Entered by VVERA1 - Not ready unit 236. 237, Receptacle in bathroom doesn’t reset. 235, no power in GFI receptacle in bathroom. 233, 232, 234, 230. 228, GFI defective. 229, 231. 225 no HVAC unit. 224 receptacle in bathroom doesn’t reset. 226 receptacle in bathroom doesn’t reset. 227 HVAC not working. 222, 220, 221, 223, 219. 218 gfi receptacle doesn’t reset. 119, exhaust fan doesn’t work. Needs casing. 118 GFI defective. 121, GFI doesn’t reset. 123, 120. 122, GFI receptacle doesn’t reset. 125 GFI defective. 127, GFI doesn’t reset. 126. 124 GFI not wired correctly. 129, 131, 128. 133, GFI wired incorrectly. 135. 134 sink not installed. 132, 137, 136. |
07/14/2022 | COT - LCBU - Building Progress | DMUNIZ | Partial Approval | Entered by NGARCIA3 - PARTIAL, west building 2nd FLOOR North guest rooms, vanity light relocation ok to proceed. |
07/07/2022 | COT - LCBU - Building Progress | DMUNIZ | Partial Approval | Entered by NGARCIA3 - PARTIAL, SOUTH BUILDING RENOVATIONS COMPLETE. |
06/17/2022 | COT - LCBU - Building Progress | DMUNIZ | Partial Approval | Entered by NGARCIA3 - PARTIAL, (SOUTH BUILDING, 2ND FLOOR), (MAIN LOBBY) ELECTRICAL IN WALLS OK TO PROCEED. |