Inspection Status: Not Ready
Inspection History: COT - LCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - LCBU - Framing |
|
Not Ready |
|
| 01/19/2023 |
COT - LCBU - Framing |
|
Partial Pass |
Inspection is for masonry pre-grout at 0” - 48”. Ok to place grout in progress areas. |
| 01/27/2023 |
COT - LCBU - Framing |
|
Partial Pass |
Inspection should read Masonry pre-grout at 4’ - 8’. Ok to place grout in progress areas. |
| 02/08/2023 |
COT - LCBU - Framing |
|
Partial Pass |
Inspection is for masonry pre-grout at level 8’ - 12’. Ok to place grout in progress areas. |
| 02/23/2023 |
COT - LCBU - Framing |
|
Partial Pass |
Inspection for masonry pre-grout at 12’ - 16’. Ok to grout progress areas. |
| 03/13/2023 |
COT - LCBU - Framing |
|
Partial Pass |
Inspection is for masonry pre-grout: CMU walls at 16’ - 20’. Straps and anchor bolt are in place. Ok to place grout in progress areas. |
| 04/03/2023 |
COT - LCBU - Framing |
|
Partial Pass |
CMU walls topped out and capped. Ok to place grout in progress areas. All CMU walls are complete except for patio area. |
| 05/11/2023 |
COT - LCBU - Framing |
|
Passed |
|