Inspection Status: Not Ready
Inspection History: COT - LCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCPL - Plumbing Progress |
|
Not Ready |
|
| 09/21/2022 |
COT - LCPL - Plumbing Progress |
WGALLAGHER |
Partial Approval |
Entered by NGARCIA3 - partial approval for 2 inch waste on north side ok to cover apex 150’
|
| 02/02/2023 |
COT - LCPL - Plumbing Progress |
|
Partial Pass |
UG rough soil and water. |
| 04/03/2023 |
COT - LCPL - Plumbing Progress |
|
Passed |
|
| 12/28/2022 |
COT - LCPL - Plumbing Progress |
|
Partial Pass |
partial approval for drain for coolers, ok to cover |