Permit: T21CM07425

Parcel: 12215299B

Inspection Status: Approved

Inspection History: PLUMBING - GAS PRESSURE TEST

Permit Number - T21CM07425

Inspection Description - PLUMBING - GAS PRESSURE TEST

Inspection Status - Approved

Date Description Inspector Results Comments
09/01/2022 PLUMBING - GAS PRESSURE TEST Approved Approved

Fire final approved under permit number T22CM07414. ON 7/1/22.
03/30/2022 PLUMBING - GAS PRESSURE TEST Partial Approval Partial. Units number two, five, six, seven, 11, 15, 16, 17, 18, 21 and 25. Unit 1 not ready. Southwest gas clearance is required.
03/07/2022 PLUMBING - GAS PRESSURE TEST Partial Approval pa

Clear gas for units:
3, 4, 8, 9, 10, 12, 14, 19, 22