Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2022 | PLUMBING - FINAL | Approved | Approved | |
| 08/23/2022 | PLUMBING - FINAL | Partial Approval | Unit 6 complete Unit 7 complete Unit 8 flew pipe not attached to water heater Unit 9 Complete Unit 10 complete |
|
| 08/17/2022 | PLUMBING - FINAL | Partial Approval | Partial approval; unit 6 need hammer arrester on DW anti tip on stove, toilet needs caulked Unit 7 no pan under WH, no flew on furnace, hammer arrester for dishwasher Unit 8 support gas pipe in closet, hammer arrester on DW Unit 9 partial approval need gas pressure test, hammer arrester on dishwasher Unit 10 need pan under WH and flew pipe installed incorrectly need hammer arrester for dishwasher |
|
| 06/30/2022 | PLUMBING - FINAL | Not ready for Inspection | Not ready. |