Inspection Status: Not Ready
Inspection History: COT - LCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - LCBU - Framing |
|
Not Ready |
|
| 06/13/2022 |
COT - LCBU - Framing |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - PA. Pending electrical in wall of Guest Services/OPU. Also rear restroom. |
| 06/10/2022 |
COT - LCBU - Framing |
IVR USER |
Cancelled |
Entered by IVR USER - IVRS - AP canceled |
| 05/05/2022 |
COT - LCBU - Framing |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Team service center room |
| 03/25/2022 |
COT - LCBU - Framing |
ESTEVENS |
Approved |
Entered by NGARCIA3 - Approved |
| 03/16/2022 |
COT - LCBU - Framing |
WGALLAGHER |
Partial Approval |
Entered by VVERA1 - Partial approval for west wall in front stock room ok to two side, ok to 2 side conference room 161, OK to 2side open office room 163 4 studs on south wall adjoining director office 160, ok to 2 side directors office 160, ok to 2 side training room 138. |
| 03/08/2022 |
COT - LCBU - Framing |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Rough frame Inspection for Break room, Training, & HR Office. Ok to one side walls and hard lid locations. |
| 12/16/2022 |
COT - LCBU - Framing |
|
Passed |
|