Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|
| 10/07/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial . West side loading dock footing and east side loading dock wall. |
| 10/05/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
IVR USER |
Cancelled |
Entered by IVR USER - IVRS - RI canceled |
| 09/29/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
East loading dock ok to pour |
| 08/18/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
Ok to pour tilt ups 23-28
|
| 08/16/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
Panels 13 to 22 ok to pour. |
| 08/12/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
SCARRAZCO |
Partial Approval |
Entered by VVERA1 - Partial. 1-12 panels are okay to pour.
|
| 08/10/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Cancelled |
Entered by VVERA1 - ca
Per Chuck
|
| 07/28/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Building slab complete. |
| 07/26/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
SCARRAZCO |
Partial Approval |
Entered by RSALDAT1 - grid line 6 to 9. Column 6 to 9 north to south and A to X East to west. |
| 07/22/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
Footings in mid section - GL 12 - 9 East to West - ok to pour |
| 06/22/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
Stems ok to pour at F-U/2.2-1 and D-F/1-0.5
|
| 06/15/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
TGAUSP |
Partial Approval |
Entered by VVERA1 - Partial, per special inspection reports, okay for concrete placement |
| 05/24/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa Interior column footings - J- 2-13 and R- 4- 19 - ok to pour |
| 05/24/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
Interior column footings - J- 2-13 and R- 4- 19 - ok to pour
|
| 05/04/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
GL 17-14 J-R. 8 column pad footings ok to pour. |
| 11/07/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
for 2 light pole footings, conduits and ufers. |
| 11/16/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
partial approval for retainer footer, NW side for handicap ramp and stair at man door, ok to place concrete |