Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|
| 09/28/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial for foundation and reinforced arches on Line B-7, 9. Okay for concrete placement of foundation and arches |
| 09/08/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
WGALLAGHER |
Partial Approval |
Entered by NGARCIA3 - Partial approval for 20’ footer at north northwest wall ok to place concrete and awning header beam from arches to existing, ok to place concrete
|
| 07/26/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. All C1 columns except for the two at the NE corner of building |
| 07/19/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, column footings @ GL-B-2,3,4,5,6,7,8 all ok for concrete placement. |
| 03/15/2023 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
|