Inspection Status: Not Ready
Inspection History: COT - LCBU - Framing
Permit Number - T21CM05961
Inspection Description - COT - LCBU - Framing
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCBU - Framing | Not Ready | ||
| 01/10/2023 | COT - LCBU - Framing | Partial Pass | North and West entry areas canopy. | |
| 02/21/2023 | COT - LCBU - Framing | Partial Pass | Interior framing is complete. Electric intermediate for offices and interior walls is complete. Ok to insulate progress areas. | |
| 03/15/2023 | COT - LCBU - Framing | Passed | ||
| 12/28/2022 | COT - LCBU - Framing | Partial Pass | Roof nailing for unit # 121. Ok to dry in roof system. |