Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Progress
Permit Number - T21CM05814
Inspection Description - COT - LCBU - Building Progress
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/19/2022 | COT - LCBU - Building Progress | Not Ready | ||
10/14/2022 | COT - LCBU - Building Progress | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for retaining wall footing 100’ east to west and 50’ north to south. And third lift on new structure with ledger ties and roof wall straps, ok to place concrete |
10/13/2022 | COT - LCBU - Building Progress | WGALLAGHER | Not ready for Inspection | Entered by NGARCIA3 - Not ready |
09/21/2022 | COT - LCBU - Building Progress | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for 2nd lift on walls for cat room addition ok to grout |
08/29/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by NGARCIA3 - pa 2 row stem on the W and SW patio walls on the W bldg, ok to grout. |
08/10/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by VVERA1 - pa West site wall footing and 9 south and east patio columns ok to pour. |
07/27/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by VVERA1 - pa Pregrout approved for west building to top out. |
07/22/2022 | COT - LCBU - Building Progress | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for 4th lift on east building ok for grouting |
07/15/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by NGARCIA3 - pa 3rd lift - 8 to 12’ for all exterior and interior wallls, ok to grout. West bldg. |
07/08/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by VVERA1 - pa 2nd lift on west building ok to grout. |
06/13/2022 | COT - LCBU - Building Progress | TGAUSP | Not ready for Inspection | Entered by VVERA1 - NR, cancelled by Contractor |
06/07/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by NGARCIA3 - pa Addition and east building slabs ok to pour |
05/09/2022 | COT - LCBU - Building Progress | DQUINN | Partial Approval | Entered by VVERA1 - pa East cat building stem wall complete for grout. |
04/25/2022 | COT - LCBU - Building Progress | DQUINN | Cancelled | Entered by NGARCIA3 - ca Per Kevin |
02/10/2023 | COT - LCBU - Building Progress | Partial Pass | partial approval for roof nailing on remaining patio covers, ok to install crickets | |
08/29/2023 | COT - LCBU - Building Progress | Passed | ||
10/21/2022 | COT - LCBU - Building Progress | Partial Pass | ||
11/03/2022 | COT - LCBU - Building Progress | Partial Pass | Partial approval for retainer wall approximately 200 feet on east side of main building first lift |