Inspection Status: Approved
Inspection History: SITE - SEWER
| Date |
Description |
Inspector |
Results |
Comments |
| 06/17/2022 |
SITE - SEWER |
|
Approved |
Approved |
| 01/31/2022 |
SITE - SEWER |
|
Partial Approval |
Partial, interconnection from Public manhole to Manhole 1 ok to backfill progress |
| 01/25/2022 |
SITE - SEWER |
|
Partial Approval |
Partial, 6” laterals from main for Buildings (1,2,3,4) ok to backfill progress areas. |
| 01/24/2022 |
SITE - SEWER |
|
Partial Approval |
Partial, 8” Sewer Main from Manhole 1-2 ok to backfill progress, Manhole 2, 3, 4 bases poured and ok to proceed. |
| 01/14/2022 |
SITE - SEWER |
|
Partial Approval |
PARTIAL, 8” sewer main from manhole 2-3 ok to backfill progress areas, except branch line locations. |
| 01/13/2022 |
SITE - SEWER |
|
Partial Approval |
PARTIAL, no inspection today see previous notes for progress. |
| 01/12/2022 |
SITE - SEWER |
|
Partial Approval |
Partial, 8” sewer main from Manhole 3-4 ok to backfill progress areas, except Branch line areas. |