Inspection Status: Canceled
Inspection History: COT - LCPL - Plumbing Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | COT - LCPL - Plumbing Final | Canceled | Inspection Canceled | |
| 09/16/2021 | COT - LCPL - Plumbing Final | DBENOIT | Prior to Final Inspectn | Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION |
| 01/17/2024 | COT - LCPL - Plumbing Final | Not Ready | ! 1/17/24: permit extension |
|
| 03/27/2026 | COT - LCPL - Plumbing Final | Re-inspection required | 3-27-26: adjust restroom door to 5pounds of pressure, secure mixing valve at restroom and insulate (ADA knee guards), secure emt cables/conduits above panel, remove tape from hood vent, add R3 insulation hot side of water heater, no power to receptacle adjacent to door by water heater, insulate backflow preventer, paint exterior plastic on rooftop, install permanent labeling at rooftop disconnect, Secure with electrical whip at A/C1's receptacle, rooftop receptacle must be weather resistant gfci, missing exhaust fan cap, seal around hood vent at rooftop. | |
| 04/01/2026 | COT - LCPL - Plumbing Final | Passed | 4-1-26: plumbing final approved. | |
| 06/18/2024 | COT - LCPL - Plumbing Final | Not Ready | 1/17/24: permit extension 6/18/24: permit extension |