Inspection History Details
Inspection Status: Canceled
Inspection History: COT - LCME - Mechanical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | COT - LCME - Mechanical Final | Canceled | Inspection Canceled | |
| 09/16/2021 | COT - LCME - Mechanical Final | DBENOIT | Prior to Final Inspectn | Entered by DBENOIT1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION |
| 01/17/2024 | COT - LCME - Mechanical Final | Not Ready | 1/17/24: permit extension | |
| 03/27/2026 | COT - LCME - Mechanical Final | Re-inspection required | 3-27-26: adjust restroom door to 5pounds of pressure, secure mixing valve at restroom and insulate (ADA knee guards), secure emt cables/conduits above panel, remove tape from hood vent, add R3 insulation hot side of water heater, no power to receptacle adjacent to door by water heater, insulate backflow preventer, paint exterior plastic on rooftop, install permanent labeling at rooftop disconnect, Secure with electrical whip at A/C1's receptacle, rooftop receptacle must be weather resistant gfci, missing exhaust fan cap, seal around hood vent at rooftop. | |
| 04/01/2026 | COT - LCME - Mechanical Final | Passed | 4-1-26: mechanical final approved. | |
| 06/18/2024 | COT - LCME - Mechanical Final | Not Ready | 1/17/24: permit extension 6/18/24: permit extension not ready |