| 11/04/2022 | COT - LCEL - Electrical Intermediate | Canceled | Inspection Canceled | |
| 01/17/2024 | COT - LCEL - Electrical Intermediate | Not Ready | New framing revision not on site, truss calcs not on site, gas test not ready, ABS vent scheduled to be rerouted. Not ready! 1/17/24: permit extension |
|
| 04/06/2023 | COT - LCEL - Electrical Intermediate | Not Ready | New framing revision not on site, truss calcs not on site, gas test not ready, ABS vent scheduled to be rerouted. Not ready! | |
| 06/18/2024 | COT - LCEL - Electrical Intermediate | Not Ready | New framing revision not on site, truss calcs not on site, gas test not ready, ABS vent scheduled to be rerouted. Not ready! 1/17/24: permit extension 1/17/24: permit extension 6/18/24: permit extension |
|
| 07/20/2023 | COT - LCEL - Electrical Intermediate | Partial Pass | south 1/2 of building | |
| 07/26/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
| 07/28/2023 | COT - LCEL - Electrical Intermediate | Not Ready | ||
| 08/08/2023 | COT - LCEL - Electrical Intermediate | Partial Pass | please install bond bushings at all panels and boxes |