Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
Permit Number - T21CM04376
Inspection Description - COT - LCBU - Excavation/Rebar/Zoning
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | ||
06/06/2022 | COT - LCBU - Excavation/Rebar/Zoning | DMUNIZ | Partial Approval | Entered by VVERA1 - Partial, Pod 2 East Foundation ok for concrete placement. |
06/03/2022 | COT - LCBU - Excavation/Rebar/Zoning | DMUNIZ | Partial Approval | Entered by NGARCIA3 - Partial, Pod 2, North Building ok for concrete placement. |
05/05/2022 | COT - LCBU - Excavation/Rebar/Zoning | DMUNIZ | Partial Approval | Entered by NGARCIA3 - PARTIAL, South & West buildings for pad 2 ok for concrete placement. |
01/10/2023 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | partial approval for five Parking lot canopy post on west side of building | |
03/13/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Completed to call him footers north side of building one OK to Place CONCRETE |