Inspection Status: Not Ready
Inspection History: COT - LCBU - Framing
Permit Number - T21CM04376
Inspection Description - COT - LCBU - Framing
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCBU - Framing | Not Ready | ||
| 10/18/2022 | COT - LCBU - Framing | TGAUSP | Not ready for Inspection | Entered by NGARCIA3 - NR, pouring concrete no access |
| 09/27/2022 | COT - LCBU - Framing | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Level #2 Room Units demising walls, sheathing from floor to deck above. Ok to sheet rock from deck above for Fire rating walls. |
| 09/19/2022 | COT - LCBU - Framing | WGALLAGHER | Cancelled | Entered by VVERA1 - Inspection canceled by contractor |
| 09/16/2022 | COT - LCBU - Framing | ESTEVENS | Partial Approval | Entered by VVERA1 - Partial. 3rd floor deck, building A and B. |
| 09/12/2022 | COT - LCBU - Framing | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for walking deck, 2nd floor only |
| 09/08/2022 | COT - LCBU - Framing | WGALLAGHER | Not ready for Inspection | Entered by NGARCIA3 - Not ready |
| 08/23/2022 | COT - LCBU - Framing | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for pod 2 building B 2nd floor deck nailing |
| 08/22/2022 | COT - LCBU - Framing | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for 2nd floor deck nailing building D pod 2 |
| 11/29/2023 | COT - LCBU - Framing | Passed |