Inspection Status: Not Ready
Inspection History: COT - RSBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - RSBU - Preslab |
|
Not Ready |
|
| 02/22/2023 |
COT - RSBU - Preslab |
|
Not Ready |
Gate was locked, no one present. Please reschedule inspection |
| 02/23/2023 |
COT - RSBU - Preslab |
|
Passed |
Ok to place concrete after termite treatment. |
| 03/17/2023 |
COT - RSBU - Preslab |
|
Passed |
|
| 03/27/2023 |
COT - RSBU - Preslab |
|
Partial Pass |
STYROFOAM block system; second lift at 5’5” - 10’. Ok to grout progress areas. |
| 04/11/2023 |
COT - RSBU - Preslab |
|
Partial Pass |
Second floor deck on plywood and 2” x 12” joists. |
| 04/17/2023 |
COT - RSBU - Preslab |
|
Partial Pass |
Inspection is for top,out for Mikey block system. Ok to grout progress areas. |