Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCEL - Electrical Underground |
|
Not Ready |
|
| 07/01/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - partial. 2 1" conduits north of soccer field. Okay to backfill.
|
| 06/28/2022 |
COT - LCEL - Electrical Underground |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial for 2- 1” conduits approximately 150’ ending at the Gate actuator on the NW side of Jr High School, okay to backfill progress areas |
| 06/21/2022 |
COT - LCEL - Electrical Underground |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial for approx. 600’ of 2- 4” power and 4- 1” underground conduit from existing SES/Transformer adjacent to softball field #1 heading east ending between softball field 1 and 2, okay to backfill progress areas |
| 03/01/2023 |
COT - LCEL - Electrical Underground |
|
Passed |
|