Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 07/18/2022 |
COT - HCBU - Preslab |
JBURGE |
Approved |
Entered by RSALDAT1 - |
| 01/12/2022 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #5, slab #15 at GL: 1-5.5/A-B. Ok to place concrete in progress areas. |
| 12/30/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - . A-B/5.5-8. Ok to place concrete in progress areas. |
| 12/01/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Level #3; Post Tension Slab #9. Ok to place concrete in progress areas. |
| 11/22/2021 |
COT - HCBU - Preslab |
JBURGE |
Not ready for Inspection |
Entered by NGARCIA3 - Not ready. Contractor cancelled; will reschedule for 23 November early am.
|
| 11/09/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #3; Post Tension Cable System on slab #6. Ok to place concrete in progress areas.
|
| 11/03/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. A-B/5.5-8; A-C/2-5.5. Ok to place concrete in progress areas. |
| 10/27/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Post Tension Cable System for ramp between Levels #2 and #3. Ok to place concrete in progress. |
| 10/20/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Post Tension Cable System inspection was performed on 19 October. |
| 10/19/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #2, Sect 3 on GL: F-J/1-5.4; H-J/5.4-8. Ok to place concrete in progress areas |
| 09/24/2021 |
COT - HCBU - Preslab |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Section #2 at GL: 1-3/D-J, D-G/3.5-5. Ok to place concrete in progress areas. |