Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Preslab
Permit Number - T21CM02423
Inspection Description - COT - HCBU - Preslab
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2022 | COT - HCBU - Preslab | JBURGE | Approved | Entered by RSALDAT1 - |
01/12/2022 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Level #5, slab #15 at GL: 1-5.5/A-B. Ok to place concrete in progress areas. |
12/30/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by NGARCIA3 - . A-B/5.5-8. Ok to place concrete in progress areas. |
12/01/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by RSALDAT1 - Partial. Level #3; Post Tension Slab #9. Ok to place concrete in progress areas. |
11/22/2021 | COT - HCBU - Preslab | JBURGE | Not ready for Inspection | Entered by NGARCIA3 - Not ready. Contractor cancelled; will reschedule for 23 November early am. |
11/09/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Level #3; Post Tension Cable System on slab #6. Ok to place concrete in progress areas. |
11/03/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by VVERA1 - Partial. A-B/5.5-8; A-C/2-5.5. Ok to place concrete in progress areas. |
10/27/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by RSALDAT1 - Partial. Post Tension Cable System for ramp between Levels #2 and #3. Ok to place concrete in progress. |
10/20/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Post Tension Cable System inspection was performed on 19 October. |
10/19/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Level #2, Sect 3 on GL: F-J/1-5.4; H-J/5.4-8. Ok to place concrete in progress areas |
09/24/2021 | COT - HCBU - Preslab | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Section #2 at GL: 1-3/D-J, D-G/3.5-5. Ok to place concrete in progress areas. |