Inspection Status: Passed
Inspection History: COT - LCEL - Grounding/Bonding
| Date |
Description |
Inspector |
Results |
Comments |
| 12/29/2021 |
COT - LCEL - Grounding/Bonding |
DMUNIZ |
Approved |
Entered by VVERA1 - Approved |
| 08/13/2021 |
COT - LCEL - Grounding/Bonding |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, EGC under slab and interconnected to uffer under slab from electrical room to water line location and disconnect.
|
| 07/21/2021 |
COT - LCEL - Grounding/Bonding |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, 20’ EGC installed in column footing, And attached to rebar ok for concrete encasement. |