Permit: T21CM01698

Parcel: 115051950


Addresses:

19 E FLORES ST

Inspection Status: Not Ready

Inspection History: RSBU - Building Progress

Date Description Inspector Results Comments
10/26/2022 RSBU - Building Progress Not Ready
12/22/2021 RSBU - Building Progress DQUINN Partial Approval Entered by NGARCIA3 - pa Roof frame, sheathing and attachment to block walls ok to cover.
12/06/2021 RSBU - Building Progress DQUINN Partial Approval Entered by VVERA1 - pa 1x12 and osb roof ok to dry in.
11/01/2021 RSBU - Building Progress DQUINN Partial Approval Entered by VVERA1 - Pa E, W, and S walls top out ok to grout
10/25/2021 RSBU - Building Progress DQUINN Cancelled Entered by NGARCIA3 - ca Per Perry
10/18/2021 RSBU - Building Progress DQUINN Partial Approval Entered by VVERA1 - pa 1st lift of 2 fill-in walls ok to grout
10/14/2021 RSBU - Building Progress DQUINN Partial Approval Entered by NGARCIA3 - Partial 3 column footers ok to pour. South and east sections of wall ok to grout 1st lift
12/14/2022 RSBU - Building Progress Passed