Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2022 | PLUMBING - FINAL | Approved | Approved ok for clearance SWG | |
| 01/20/2022 | PLUMBING - FINAL | Cancelled | nspection canceled by contractor | |
| 01/19/2022 | PLUMBING - FINAL | Partial Approval | Partial approval tempered shower glass missing | |
| 01/18/2022 | PLUMBING - FINAL | Not ready for Inspection | Not ready | |
| 01/14/2022 | PLUMBING - FINAL | Not ready for Inspection | Not ready | |
| 01/06/2022 | PLUMBING - FINAL | Partial Approval | PA SWG clearance required |
|
| 01/04/2022 | PLUMBING - FINAL | Not ready for Inspection | Not ready |