Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 02/01/2022 |
MECHANICAL - ABOVE CEILING |
|
Approved |
. Approved. |
| 11/05/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
2036, 3036, 4036. Partial. Level 2. Northwest section. |
| 11/02/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial. Level 2. Southwest corner section of building. |
| 10/27/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
1036, 2036, 3036, 4036. Partial. Level 2. Northeast section. |
| 10/14/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
1036,2036, 3036, 4036, 1044. Partial. Level 1. West side of building. |
| 10/08/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial. Level 1. East side only. |
| 06/15/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial. Level #1; Low Pressure Supply air lines at GL: A1-A4/D1-D4. Ok to insulate progress areas. |
| 06/11/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial. Second level. From gridlines D1 to D3 and H1 to H3 |
| 05/24/2021 |
MECHANICAL - ABOVE CEILING |
|
Not ready for Inspection |
NOT READY NOT COMPLETE |