Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2021 | BUILDING - FINAL | Approved | Approved | |
| 12/03/2021 | BUILDING - FINAL | Partial Approval | Partial. Contractors need to submit, a letter, on company letterhead, stating that all construction work meets or exceeds the 2018 IRC. | |
| 11/23/2021 | BUILDING - FINAL | Denied | DENIED. Built without inspections, Special Inspection required for structural compliance of building. No approved plans on site, could not perform any additional inspections. Please verify approval of 2nd kitchen… previous comments must also be addressed: 11/3/21 - Not ready need to verify all gfi circuits by continuity check inside and out, please expose hold-downs installed on either side of garage door and gain engineering approval for as built, need hammer arrester on dishwasher and mechanical was not inspected |
|
| 11/03/2021 | BUILDING - FINAL | Not ready for Inspection | Not ready need to verify all gfi circuits by continuity check inside and out, please expose hold-downs installed on either side of garage door and gain engineering approval for as built, need hammer arrester on dishwasher and mechanical was not inspected |