Inspection Status: Passed
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 08/16/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Approved |
Entered by VVERA1 - Approved |
| 04/12/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. North court yard CMU wall footing. |
| 04/05/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Light pole at west entrance. |
| 03/17/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Two sump pumps, boiler room and rise room. |
| 01/11/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by RSALDAT1 - . Partial. Handicap ramp walls. |
| 01/03/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by VVERA1 - Partial. Room C102. Two pour back strips with #4 and 5 dowels. |
| 12/15/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Footing for1
ramp. |