Inspection Status: Continued
Inspection History: TDOT-Routine Barricade Inspect
| Date |
Description |
Inspector |
Results |
Comments |
| 12/21/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
*** Congress Broadway I 10 Frontage Rd. contractor has finish all four quadrants of the intersection thermoplastic new crosswalk and bike lane JOB COMPLETE*** |
| 12/21/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
*** 22nd St. and I 10 Frontage Rd. contractor has finish thermal plastic all four quadrants of the intersection crosswalk area along with bike lane JOB COMPLETE *** |
| 12/17/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
Saint Marys and I 10 Frontage Rd *** COMPLETED*** |
| 12/17/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
Covid Slow Street Project Congress St , Broadway Blvd & I-10 Frontage Rd T20RW06450 contractor working in the area installing Termoplastic, traffic control setup |
| 12/15/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
contractors continuing to Thermal Plastic, traffic control is set up, remind contractor safety of workers due to high volume traffic |
| 12/14/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
CoVid Slow Street project T20RW06450 I-10 Frontage Rd & St Marys Rd Pre Con meeting contractor will re-strip all 4 corners of the intersection along with under the bridge with Thermoplastic, traffic control reminder not to set up before 8:45 AM and must be off the street by 3:00 PM |