Inspection Status: Continued
Inspection History: TDOT-Routine Barricade Inspect
| Date |
Description |
Inspector |
Results |
Comments |
| 12/15/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
42nd St. and prudence T20RW046914 4 speed humps installed, all side markers installed, RPMs installed, thermal plastic on all speed humps complete / very nice job, signage for Speed hump ahead? complete, All traffic control has been removed 100% completed? |
| 12/01/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
CoVid slow Street project T20RW04691 per request Bob our check on location 42nd St. and Prudence contractor stating job has finished took photos of speed humps , signage , side markers at speed humps and temporary striping complete no Thermal Plastic or RPM have been installed |
| 11/16/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
CoVid slow street project location 42nd St. and Prudence T20RW04691 speed humps complete contractor has painted with temporary striping, side markers for speed humps pending |
| 11/12/2020 |
TDOT-Routine Barricade Inspect |
|
Continued |
CoVid Slow sweets project location prudence and 42nd St. for speed humps complete Address 7525, 7611 , 7635 E. 42nd St. & near the intersection of Mark Drive and David Drive |
| 09/28/2020 |
TDOT-Routine Barricade Inspect |
|
Not ready for Inspection |
NO TRAFFIC CONTROL |